04 / PROJECT DETAIL
Midi Tailings Storage FacilityGümüşhane
Lasting value in water infrastructure.
ABOUT THE PROJECT
Safe design. Long-term value.
Final and detailed designs for the Midi Tailings Storage Facility in Şiran, Gümüşhane. The mine tailings dam developed for Yıldızlar SSS Holding has a recorded design height of 41 m.
41 mTailings dam height
Final and detailed designsService
Tailings storageEngineering discipline
ENGINEERING APPROACH
From scientific analysis to practical solutions.
Our multidisciplinary approach brings technical, environmental and economic criteria together.
Our technical approach- 01
Storage and safety
Integrated consideration of site conditions, storage geometry and water management.
- 02
Engineering design
Developing coherent design decisions with safety, feasibility and resource efficiency in view.
- 03
Technical coordination
Coordinating disciplines, drawings and technical documentation within the scope of the assignment.